Copyright 2013, Ron Minor

NOTE - No part of this blog or the link to it maybe cross posted without the permission of the blog writer!!

Copyright 2013, Ron Minor

Saturday, July 21, 2012

Blair Sub Construction Update

Over the past couple of weeks I have been able to get out and explore the work being done on the new double track the UP is building on the Blair Sub. Since my last report there has been some significant progress made on the Iowa side as well as the area from Kennard to Arlington, NE.

On the 7th I as able to do some exploring on the Iowa side of the project. At that time the new second main had been ballasted and the new cross over switch east of Italy Ave had been installed installed. The main had been extended as far as Allen Creek but had not been cut into the existing second main. Westbound movements still had to take the switch at Allen Creek to access the single track sub.
MKCVP passing through Allen Creek by the end of the new double track.
New second main looking west toward California Jct., IA
On the 14th one of the areas infamous mentally and socially unstable super foamers reported that the new double track section from Allen Creek to just east of California Jct was now open. Interestingly (probably telling of his status) no one replied to his notice.

During my trip to this area on the 20th it was observed that the new second main was indeed completed and being used. While looking over the area west from Italy Ave, I noticed that the old main had a MOW mobile welding truck on it and the third main contained around 20 ballast cars parked on it. A curious observation on the third main is that the eastern most 20 feet of track had been cut and stacked on top of  the continuous track.

UP 6747 leads a eb empty auto rack train on the new second main at Italy Ave west of Missouri Valley, IA.
At California Jct., IA the old CNW search light signals have been retired and pointed away from the main in favor of the new UP Darth Vader signals. Track sub grade work has stopped short of the west Fremont Ave crossing. Utility poles are being installed that will clear the new ROW both horizontally and vertically. Once this is completed the little bit of remaining ROW work should be finished rather quickly.

Looking west from Fremont Ave at California Jct., IA.
Current junction for the end of double track east of California Jct., IA.
Old CNW search lights have been replaced by new signals at California Jct., IA.
On both sides of the Austin Ave crossing I noted that the UP had laid down asphalt on top of the sub grade fines. I had only seen this done once before by the BNSF in western TX on the double tracking of the transcon. I am guessing this was done to add more stability to the row as this is old river bottom land and can get water logged during wet times.

Another interesting item was noted on the east side of the Austin Ave crossing. Four corrugated pipes around 12 inches in diameter are sticking up about a foot out of the ground in a square grid pattern. I'm not sure what these are for and can only assume its for signals.

The bridge over the slough between Austin and Corning Avenues is completed and ready for ties and track to be laid. The row is also completed up to the Corning Ave from the east.

Asphalt sub base west of Austin ave crossing.
West of Corning Ave there has been another dramatic change in the past two weeks. On the 7th I noted that grading of the new row toward the river had started. On the 20th this work had progressed to the point were the new row has the sub base fines laid down. On the north side of the existing row grading is occurring and trucks hauling in dirt were noted dumping there loads about half way up the incline to the Missouri River bridge.
A look out sits on the freshly built row as grading continues on the northwest side of  the Corning Ave crossing.
It is difficult to see what is actually occurring on the north side of the row west from Corning Ave as roads are not readily available. There is a county road that does go under the Hwy 30 bridge to the north side but is it closed except to construction crews. A grader and trucks dropping loads were seen across the fields along the southwestern running tangent but no real detail could be seen.

From the Blair, NE side of the river I could not see any activity on the Iowa side. I did notice that there is excavation work and pilings be positioned just north of the public boat ramp. I do not know if this is work being done by the city or part of the UP project. A curious note is this work does line up with the old SC&P row that lead to the river ferries back in the late 1880's.

West from Blair no other work was noted until Kennard, NE. The bridge work that had been reported previously is now completed on the old Kennard siding. The old row has been regraded and sub base fines laid down and compacted. Ribbon rail has been laid next to the new row and the row is being prepped for ties and the rail to be installed.

Looking west along the old Kennard siding.
From the area of the old West Kennard siding to Co Rd 21, the row grading has been completed and the sub base fines laid down. Culvert and bridge work is also completed and the row is nearly ready for ties and rail to be installed. Looking west from the Co Rd 21 crossing the new row is clearly visible with the white rock sub grade laid down. It appears that the existing track will deviate into the new cut and the new track will cross the existing line. When the time comes for this cut over it will result in the line being shut down while for awhile. These typically occurs on Mondays when traffic on the sub is low.

Looking west from Co Rd 21 at new row.

Looking east toward Kennard from Co Rd 21.
On both sides of the Co Rd 19 crossing the row grading is completed and the sub base fines have been installed. At the top of Arlington Hill the excavation work on the cutting back of the hill to the east has been completed along with the installation of the bridge east of the hill. Grading and sub base fines have been laid and the row is nearing completion for ties and rail to be installed.

Looking up grade west from Co Rd 19.
The area around Co Rd 15 is still under construction. It is here where the line will be dramatically changed, The s-curve west of the crossing will be removed and the line shifted to the north from its present location at the crossing. Some of the sub grade has been completed west of Co Rd 15 heading down grade toward Arlington, but this section is not complete.


The s-curve west of Co Rd 15 that will be eliminated.
At Co Rd P11 heavy equipment was seen working the new row up to the creek. West from the creek up to the grain elevator on the east side of Arlington, NE, row work has started. 

From Arlington west to Fremont no work has begun.

Heavy equipment working west of Co Rd P11.


Sunday, July 08, 2012

BNSF Plattsmouth bridge update

On Friday June 29th, I ventured over to the Pacific Jct, IA - Plattsmouth, NE area to check on the progress of the BNSF's new Missouri River bridge. Due to some issues this will be my last report on this construction project.

Starting in Pacific Jct we headed west on old Hwy 34 toward Plattsmouth. The first stop was the crossing on 190th st to take a look at what the BNSF has been doing. Looking east from the crossing crews are working on the ROW preparing it for the second main.

Looking east toward Pacific Jct from 190th st.

This area had been built up last year to protect the line from the Missouri River flooding. The ROW is now about 6 feet taller than before the flooding, but the extra levees that were built on both sides of the elevated main have been removed. Looking west from the crossing the extra dirt appears to have been leveled and used for the second main ROW.

View west from 190th st toward NE.

From 190th st I turned left on Kane Ave which parallels the main on the north side for about a minle. At the creek crossing I noticed a new double track bridge had been installed since last year. A review of Google earth shows the bridge was under construction on the 03/07/12 imagery.

New double track concrete bridge.
Looking east toward the new bridge from 180th st. There is an usual kink in the track closer to the bridge.
Kane Ave is closed at 18th st and to get back to the tracks I turned south. At the 180th st crossing crushed rock and dirt trucks are entering the ROW and making dumping runs toward the new bridge. There was a construction contractor staging the trucks and taking their paperwork at the crossing. He was more concerned about the trucks that me which as we will see is not always the case.

Rock truck heading to the current rock dumping spot.


The elevation of the new fill is nicely shown in this shot from Hwy 34

A rock truck that has come off the fill to head west  across the river.

Back on Hwy 34 I headed over to the east end of the Plattsmouth toll bridge and parked on the south shoulder of the road. Taking a look at the amount of progress that is occurring there must be a bonus if the construction companies complete this project ahead of time.

Iowa side work area


Iowa side bridge footing and pier area.
The earth work on the NE side is still ongoing and I was not able to see to what level the work was at other than dust and truck activity. What was a nice suprise was the completion of the west side bridge footing and first pier. The first spans were also noted having been installed on the west side. The east side of the river showed that the piers where being built or closed to being finished but there was no indication that the peir that will be in the river was being constructed yet.

The other contractor.

As soon as I stepped out of my vehicle this individual jumps out of his truck and wants to know what he can do to help me. I replied nothing and that I was taking pictures. His immediate reply was that the BNSF does not want or allow anyone to take photos of this construction project. I was determined to get my photos and to stand my ground as I am on a public highway, so I asked him since when did the BNSF but Hwy34. His short reply was that its illegal to take photos and that I was trespassing and to leave the area immediately. Hmmm...nope not going to happen. I continued to take my photos while the contractor was taking video and photos of me.



BNSF Contractor 
The contractor followed me across the bridge and when I parked in the parking area across from the toll booth to get some more photos, he was observed having an animated conversation with the toll booth collector. As I return to my vehicle the toll booth operate runs out of the tool booth shouting and swearing for all he was worth that i was to get off the public road and get out of there.

Contractor at the tool booth


The short version of the ensuing conversation and threats from the tool booth operator was the BNSF did not want me there and that I was trespassing; on a public highway. Well the individual finally disengaged from me and I proceeded into Plattsmouth. As I was driving into the town, the contractor was observer following me until I turned into the area were the county law enforcement center is. Needless to say the day ended with me filing out a police report for harassment and sharing my photos with the county sheriff and my girlfriend being less than impressed with the whole situation.

As I indicated above this is my last report on this construction project.