Over the past couple of weeks I have been able to get out and explore the work being done on the new double track the UP is building on the Blair Sub. Since my last report there has been some significant progress made on the Iowa side as well as the area from Kennard to Arlington, NE.
On the 7th I as able to do some exploring on the Iowa side of the project. At that time the new second main had been ballasted and the new cross over switch east of Italy Ave had been installed installed. The main had been extended as far as Allen Creek but had not been cut into the existing second main. Westbound movements still had to take the switch at Allen Creek to access the single track sub.
|
MKCVP passing through Allen Creek by the end of the new double track. |
|
New second main looking west toward California Jct., IA |
On the 14th one of the areas infamous mentally and socially unstable super foamers reported that the new double track section from Allen Creek to just east of California Jct was now open. Interestingly (probably telling of his status) no one replied to his notice.
During my trip to this area on the 20th it was observed that the new second main was indeed completed and being used. While looking over the area west from Italy Ave, I noticed that the old main had a MOW mobile welding truck on it and the third main contained around 20 ballast cars parked on it. A curious observation on the third main is that the eastern most 20 feet of track had been cut and stacked on top of the continuous track.
|
UP 6747 leads a eb empty auto rack train on the new second main at Italy Ave west of Missouri Valley, IA. |
At California Jct., IA the old CNW search light signals have been retired and pointed away from the main in favor of the new UP Darth Vader signals. Track sub grade work has stopped short of the west Fremont Ave crossing. Utility poles are being installed that will clear the new ROW both horizontally and vertically. Once this is completed the little bit of remaining ROW work should be finished rather quickly.
|
Looking west from Fremont Ave at California Jct., IA. |
|
Current junction for the end of double track east of California Jct., IA. |
|
Old CNW search lights have been replaced by new signals at California Jct., IA. |
On both sides of the Austin Ave crossing I noted that the UP had laid down asphalt on top of the sub grade fines. I had only seen this done once before by the BNSF in western TX on the double tracking of the transcon. I am guessing this was done to add more stability to the row as this is old river bottom land and can get water logged during wet times.
Another interesting item was noted on the east side of the Austin Ave crossing. Four corrugated pipes around 12 inches in diameter are sticking up about a foot out of the ground in a square grid pattern. I'm not sure what these are for and can only assume its for signals.
The bridge over the slough between Austin and Corning Avenues is completed and ready for ties and track to be laid. The row is also completed up to the Corning Ave from the east.
|
Asphalt sub base west of Austin ave crossing. |
West of Corning Ave there has been another dramatic change in the past two weeks. On the 7th I noted that grading of the new row toward the river had started. On the 20th this work had progressed to the point were the new row has the sub base fines laid down. On the north side of the existing row grading is occurring and trucks hauling in dirt were noted dumping there loads about half way up the incline to the Missouri River bridge.
|
A look out sits on the freshly built row as grading continues on the northwest side of the Corning Ave crossing. |
It is difficult to see what is actually occurring on the north side of the row west from Corning Ave as roads are not readily available. There is a county road that does go under the Hwy 30 bridge to the north side but is it closed except to construction crews. A grader and trucks dropping loads were seen across the fields along the southwestern running tangent but no real detail could be seen.
From the Blair, NE side of the river I could not see any activity on the Iowa side. I did notice that there is excavation work and pilings be positioned just north of the public boat ramp. I do not know if this is work being done by the city or part of the UP project. A curious note is this work does line up with the old SC&P row that lead to the river ferries back in the late 1880's.
West from Blair no other work was noted until Kennard, NE. The bridge work that had been reported previously is now completed on the old Kennard siding. The old row has been regraded and sub base fines laid down and compacted. Ribbon rail has been laid next to the new row and the row is being prepped for ties and the rail to be installed.
|
Looking west along the old Kennard siding. |
From the area of the old West Kennard siding to Co Rd 21, the row grading has been completed and the sub base fines laid down. Culvert and bridge work is also completed and the row is nearly ready for ties and rail to be installed. Looking west from the Co Rd 21 crossing the new row is clearly visible with the white rock sub grade laid down. It appears that the existing track will deviate into the new cut and the new track will cross the existing line. When the time comes for this cut over it will result in the line being shut down while for awhile. These typically occurs on Mondays when traffic on the sub is low.
Looking west from Co Rd 21 at new row.
|
Looking east toward Kennard from Co Rd 21. |
On both sides of the Co Rd 19 crossing the row grading is completed and the sub base fines have been installed. At the top of Arlington Hill the excavation work on the cutting back of the hill to the east has been completed along with the installation of the bridge east of the hill. Grading and sub base fines have been laid and the row is nearing completion for ties and rail to be installed.
|
Looking up grade west from Co Rd 19. |
The area around Co Rd 15 is still under construction. It is here where the line will be dramatically changed, The s-curve west of the crossing will be removed and the line shifted to the north from its present location at the crossing. Some of the sub grade has been completed west of Co Rd 15 heading down grade toward Arlington, but this section is not complete.
|
The s-curve west of Co Rd 15 that will be eliminated. |
At Co Rd P11 heavy equipment was seen working the new row up to the creek. West from the creek up to the grain elevator on the east side of Arlington, NE, row work has started.
From Arlington west to Fremont no work has begun.
|
Heavy equipment working west of Co Rd P11. |